The Real Timeline of Building a House in NSW
The honest timeline of building a home in NSW is longer than most owners expect. Here is what really happens.
Month 1-2: Discovery
Find a builder, walk display homes, get initial quotes. Decide on tier (project, custom, or somewhere between).
Month 3-5: Design and selections
Architectural drawings, BASIX, NATHERS, engineering. Make every selection: facade, floor plan modifications, kitchen, bathrooms, fixtures, fittings.
Month 5-6: Contract and finance
Final contract review with lawyer. Bank finance approved. Contract signed. Deposit paid.
Month 6-10: Approvals
CDC: 8 to 10 weeks. DA: 12 to 30 weeks. While waiting, finalise any remaining selections.
Month 10-12: Pre-construction
Council requirements addressed. Construction Certificate issued. Site prepared. Demolition (if KDR). Slab pour.
Month 12-22: Construction
Stages: slab, frame, lockup, rough-in, fixing, finishing. Typically 8 to 11 months from slab to handover.
Month 22-24: Handover
Final inspection, defects rectification, Occupation Certificate, keys.
Ready to start? Or want to plan further out?
Free consultation. We will give you a realistic timeline for your specific situation.
Quick Answers
Thinking of building or renovating in Western Sydney?
Book a free, no-obligation consultation. We will walk through your block, your brief and your budget, and tell you honestly whether 13 Homes is the right builder for the job.
Book a Consultation